ANALISIS PENJADWALAN WAKTU MENGGUNAKAN METODE CPM DAN PERT PADA PEMBANGUNAN GUDANG DEXA MEDICA PALEMBANG

Authors

  • Lega Reskita Lubis Jurusan Teknik Sipil Politeknik Negeri Sriwijaya
  • Zuul Fitriana Umari Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tridinanti
  • Kristi Kristi Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tridinanti
  • Akhirini Akhirini Program Studi Teknik Sipil, Fakultas Teknik, Universitas Tridinanti

DOI:

https://doi.org/10.52333/lateral.v1i2.314

Keywords:

CPM method, PERT method, Critical path, Probability

Abstract

The project is a series of sensitive work mechanisms because each aspect of the project is interconnected with each other. The purpose of this research is to determine the planned duration, critical path activities, and probability in the implementation of the Dexa Medica warehouse construction project in Palembang. Primary data used for estimation of work time, while secondary data used time schedules (S-curve) and work plan drawings. The methods used are the Critical Path Method (CPM) and the Program Evaluation and Review Technique (PERT). The planned project completion duration using the CPM calculation method is 39 weeks. The activities known to be on the critical path are preparation, earthworks and others on the 1st floor, concrete work on the 1st floor, architectural work on the 1st floor, site development, and genset room work. The planned project completion duration using the PERT calculation method is 40.2 weeks. The probability (Probabiliti) with the PERT method is found to be 0.7324, meaning that there is a 73.24% probability that the project will be completed within 41 weeks.

References

Daulay, M. T., Munarsih, E., Muafiqie, H., Alkadrie, S. A., Sukasmanto, S. E., John Suarlin, S. E., & Suparman, S. E. (2022). Konsep Dasar Manajemen Proyek di Era 4.0. CV Rey Media Grafika.

Hosaini, H., Hartoto, H., Alfiana, A., Sitindaon, C. D., Saptaria, L., Rudi, R., ... & Kristiana, R. (2021). Manajemen proyek.

Effendy, K. (2020). Penjadwalan Ulang Pekerjaan Finishing Proyek Shangrila Hotel Resort and Spa Menggunakan Metode Pert Dan Flash (Doctoral dissertation, Fakultas Teknik Universitas Jember).

YuliartyP., AnggrainiR., & WastionoT. (2020). PENJADWALAN PROYEK MESIN AUTO ASSEMBLY MEMBRANE REGULATOR VALVE DI PT. OMG METODE CRITICAL PATH METHOD (CPM). Industri Inovatif : Jurnal Teknik Industri, 10(1), 21-31.

Padhil, A., Anwari, M. S., Mail, A., & Hafid, M. F. (2022). Evaluasi Penjadwalan Proyek Kapal Penyeberangan RO-RO 500 GT Melalui Pendekatan Metode CPM Dan PERT Studi Kasus PT. XYZ. Jurnal Rekayasa Industri (JRI), 4(2), 80-86.

Tamalika, T., Maryadi, D., Hermanto, M. Z., Fuad, I. S., & Alamsyah, M. N. (2022, June). Analisis Penjadwalan Ulang Proyek Power House pada Rumah Sakit dengan Metoda PERT, CPM dan Fishbone Diagram (Studi Kasus Pada Kontraktor Di Kota Palembang). In Prosiding Seminar Nasional Mercu Buana Conference on Industrial Engineering (Vol. 4, pp. 164-172).

Putra, J. G., & Sekarsari, J. (2020). Analisis penjadwalan proyek gedung bertingkat dengan metode PERT dan M-PERT menggunakan simulasi Monte Carlo. JMTS J. Mitra Tek. Sipil, 3(3), 533.

Alcaesar, M. R., & Hariyadi, E. S. (2023). ANALISIS WAKTU PELAKSANAAN PROYEK MENGGUNAKAN METODE SIMULASI MONTE CARLO (STUDI KASUS: PROYEK REHABILITASI JALAN SENTUL–TERAS BENDUNG–TIRTAYASA KABUPATEN SERANG–BANTEN TA. 2022). TEKNIKA: Jurnal Teknik, 10(1), 79-89.

Firda, A. F., Asmawi, B., Akhirini, A., & Parlaungan, D. (2023). Produktivitas Dan Efektivitas Alat Berat Pada Pekerjaan Lapis Pondasi Proyek Rehabilitasi Jalan. Jurnal Deformasi, 8(1), 100-110.

Firda, A. (2023). PRODUKTIVITAS PEKERJA DENGAN MENGGUNAKAN METODE WORK SAMPLING (PEKERJAAN PEMASANGAN TIANG PANCANG). Jurnal Teknik Sipil LATERAL, 1(1), 15-25.

Downloads

Published

2023-11-30

How to Cite

Lubis, L. R., Umari, Z. F., Kristi, K., & Akhirini, A. (2023). ANALISIS PENJADWALAN WAKTU MENGGUNAKAN METODE CPM DAN PERT PADA PEMBANGUNAN GUDANG DEXA MEDICA PALEMBANG. Jurnal Teknik Sipil LATERAL, 1(2), 21–30. https://doi.org/10.52333/lateral.v1i2.314